Development Timeline

Picture

Project Milestones
June 2018
August 22, 2018
October 3, 2018
November 14, 2018

February 11, 2019
March 12, 2019


November 5, 2019
​December 9, 2019
February 7, 2020
​May 21, 2020
January 11, 2021
​January 26, 2021
​December 11, 2021

March 1, 2022
April 20, 2022
May 7, 2022
June 30, 2022
​August 18, 2022
August 24, 2022
Fall 2024

Supervisor Tang Community Coffee 
MidPen hosted Community Meeting #1
MidPen hosted Community Meeting #2
Submit Preliminary Planning Application (PPA)
MidPen hosted Community Meeting #3 
Submit Entitlement Application, including Environmental Review, to the SF Planning Dept
SF Voters Pass Proposition E, allowing for an expedited entitlements process
MidPen submits Site Permit to Department of Building Inspections (DBI)
MidPen submits SB-35 and State Density Bonus Applications
SB-35 Application approved, thereby securing entitlements
Site Permit approved by DBI
New project name selected: Shirley Chisholm Village
SF Planning & MidPen hosted Zoom Community Meeting on Playland
​Final financing application submitted
Demolition permit issued
​Playland Closing Party hosted by SF Planning
​Playland Closed
Construction Financing Closed
Construction Starts
Anticipated Lease Up

Shirley chisholm village Location

CONTACT US

    Subscribe FOR PROJECT UPDATES

Submit
Picture
Shirley Chisholm Village is an affordable housing community currently under development by MidPen Housing. Copyright © 2022 MidPen Housing Corporation. All rights reserved.